Refrigeration installation including cabinets, coldrooms, refrigeration plant, leak detection, alarm & monitoring system and ventilation.


Wing Yip is now widely recognised as the UK’s leading Chinese and Oriental Supplier with stores and national distribution networks supplying the majority of Chinese restaurants and takeaways throughout the country. They are an established family business with two generations of the Wing Yip family currently involved along with 40 years experience, which enables quality and innovative products to be sourced.

The Group’s head office is based in Birmingham with warehousing and a national distribution centre along with superstores located in Birmingham, Manchester, Cricklewood and Croydon.

Back of House Coldrooms

Project Overview

Carter Synergy has delivered a full turnkey refrigeration package consisting of cabinets, refrigeration plant, cold storage, leak detection, alarm and monitoring, heat reclaim, ventilation and on-going service and maintenance.

The project was split into three areas namely;

Existing Unit 7: Chiller and Freezer Coldroom works including plant.
Main Store Extension: Cabinet and Coldroom works including plant.
New Build: Railway Terrace: Freezer Coldroom works including plant.

As Wing Yip continue to develop within their market place, extreme pressure is applied to the engineering element to deliver and offer continued support in order to provide a trouble-free operation throughout its life span.

Sales Floor

Carter Synergy delivered a first-class installation incorporating the requirements of the client whilst working closely with the consultant. The refrigeration plant runs on R404A and the refrigeration packs (dual temperature and low temperature) installed have been built and tested by Carter Synergy. Furthermore, all design, project management, installation, commissioning c/w service and maintenance have been completed in house, using directly employed staff and engineers.

The project required intense design and communication with Wing Yip, the Consultant and the Architect. With further projects due in the near future, the experience gained will be invaluable for the future partnership of Carter Synergy and Wing Yip.

Project Duration

The project duration was in excess of 12 months with on-going works expected based on the vast amount of refrigeration employed at Birmingham.